Change an activity code in X1
                          
                              
                            
                              
                                Updated 
                                by
                                Heather Jones
                              
                          
                          How to change a code
- Under Estimate items, select the Items tab.
 - Select an item below the Quick entry pane.
 - In the Quick entry pane, click the Act drop-down menu, and select a new activity code.
 
Code options
- + Replace: Covers the cost of installation labor and new material. 
 - - Remove: Covers the cost of removal labor. 
 - R Detach & Reset: Covers the cost to remove the existing material and reinstall it. 
 - & Remove and replace: Covers the cost of removing the old material and replacing it with new. 
 - F Repair: Only available in custom line items where a custom price is entered. 
 - M Material Only: Covers the cost of material only, not any installation costs. 
 - I Install Only: Covers the cost of the installation only, not any material costs.